Demo Iteration 3 - March 15th
Today the demonstration will consist of the following done tasks:
- Working Web site uploading section- Configured portforwarding
- Working database of club's members
- Working software for editing web page easily
- Fixed requirements, stake holders and block diagram
Demo Iteration 2 - March 8th
This demo will consist an overview of the tasks that were completed during the iteration:
- Decide on background story
- Install and configure Webserver
- Install Firewall
- Install Proxy server
- Install Database server
- Install phpMyAdmin and create database
A demonstration will be made and some questions will be taken.
Demo Iteration 1 - March 1st
For it's first demonstration the group will take a look in the vital statistics such as:
- Stakeholders
- Requirements
We will also show some diagrams:
- Overview of the system
- System usage
A brief description of the SCRUM methods we are trying to implement in the project will be done.
- Stakeholders
- Requirements
We will also show some diagrams:
- Overview of the system
- System usage
A brief description of the SCRUM methods we are trying to implement in the project will be done.
And the made progress will be overlooked.
Demo dates:
1) Tuesday 1 Mar
2) Tuesday 8 Mar
3) Tuesday 15 Mar
4) Friday 18 Mar