Tuesday, March 15, 2011

update tasklist for iteration 3

update tasklist done
make summery of iteration 3
decide in security level
define subnet for client and server working
configure NAT working
configure proxy filtering
test network
set rules for firewall
confiigure network inc privat network and NAT done
test network from inside and outside
allow upload section on webpage done
allow easy editing of the web page done
configure port forwarding working
correct requirements stake holders block diagram done
make database of members done
loging to logserver done
do customer meeting done